Improving mine compressed air network efficiency through demand and supply control
Abstract
Eskom is in a position where they are producing sufficient electricity, although rapid expansion
and an increase in demand throughout various sections in South Africa can be expected in the
future. Large electricity intensive industries such as gold and platinum mines can assist by
reducing their electricity demand.
Platinum mines are required to increase production output while keeping their overheads as
low as possible. One of the areas that can be targeted to reduce operating expenses is mining
services such as compressed air.
A compressed air network is one of the most ineffective and electricity intensive systems found
on a platinum mine. This provides opportunities for implementing Eskom funded demand side
management initiatives to decrease the electricity consumption on mining systems, which leads
to a reduction in electricity consumption costs.
Demand side management initiatives were implemented on two case studies as means to
provide electricity and cost savings. Control philosophies were developed, implemented and
optimised to ensure a decrease in electricity consumption. A simulation was constructed for
each case study and the effect of the control philosophy was simulated and quantified. Each
simulation was verified using data from the respective mines’ databases.
In Case Study 1, automated control valves were implemented at each compressed air user and
the pressure set point was decreased in the Eskom evening peak period. The flow through the
compressors were reduced and/or stopped while adhering to system and operational
constraints.
This resulted in electric power savings of 3.1 MW, which lead to an annual cost savings of
R1.9 million. The initial calculations showed that 3.9 MW could be saved, although this was
not achieved. It was determined that if repair compressed air leaks was included in this
initiative, the target could be met.
In Case Study 2, a theoretical initiative was simulated. The effect on electricity consumption
was investigated by replacing a single large 15 MW compressor with two less electricity
intensive 4 MW compressors. The investigation showed that 76 042 MWh energy efficiency
savings per day could be achieved with this initiative. This possible project would have an
annual cost saving of R20 million.
In this study, it will be shown that a compressed air network can be optimised. These
optimisations proved that electricity cost savings can be achieved for the platinum mining
industry. In both case studies, it was seen that electricity consumption can be lowered.
Collections
- Engineering [1418]